Distribution

System Operator

Network information

Substation.png
FIELDON INVESTMENTS SP. Z O.O. GRYF Sp. Jawna

FIELDON INVESTMENTS SP Z O O GRYF SPÓŁKA JAWNA has been operating as a distribution system operator since 2019 and provides electricity distribution services in the Gryfino poviat in the Zachodnipomorskie voivodeship, located in northwest Poland.

 

The current list of electricity sellers with whom the electricity distribution system operator has concluded contracts for the provision of electricity distribution services:

  • AXPO Polska sp. Z o.o.


In 2021, the network is planned to be expanded in the following areas:

  • Nowe Czarnowo substation, 110kV and 220kV fields with a power transformer of 120-140 MVA along with the technical infrastructure necessary for the supported operation of the devices

 

  •  modernization of the 110kV line in order to modernize the Banie 3 wind farm or build a new 110kV line

 

  • construction of a power station to the extent necessary to evacuate power from the new Banie 3 or Banie 3 and Banie 4 wind farms.

Network

Main elements :

  • 220kV cable starting from the current 220kV head terminals in the area of SE Krajnik and ending with the current 220kV terminals in the area of 220/110/30kV GPZ Nowe Czarnowo

  • SubStation 220/110/30kV GPZ Nowe Czarnowo

  • 110kV cable line between GPZ Nowe Czarnowo and GPO Kozielice with a length of 28.6km

Customers

DSO connected the Banie wind farm stage 1 and 2 with a total capacity of 106 MW to the 110 kV grid.
 

  • On November 3, 2018, the DSO issued the conditions for connection to the medium voltage grid for a commercial company developing a wind farm project with a total capacity of 81.4 MW.

 

Connection location: Banie 110kV / 30kV electricity substation located in Lubanów in the Banie commune.

 

  • On November 26, 2019, the DSO issued the conditions for connection to the medium voltage grid for a commercial company developing a wind farm project with a total capacity of 56 MW.


Connection location: Banie 110kV / 30kV electricity substation located in Lubanów in the Banie commune.
 

  • Until the end of Q2 2022, no entity other than the above has submitted an application for the issuance of connection conditions.

 

  • The available DSO connection capacity at the end of Q2 2022 is 0 MW.


Currently, the DSO does not plan to change these values ​​in the next 5 years (information available at the end of Q2 2022).

updated:  30/06/2022, detailed information about the above is described in the connection information tab.

 

 

IRiESD

Gryf grid code was created based on EU regulation, and the polish Energy Regulatory Office. 

 
 

Contact us

Contact us

For any questions, additional information please fill out the form below:

Main Office

Plac Małachowskiego 2

00-066 Warszawa

 

Gryf_DSO@ENERGIX-GROUP.COM

Thanks for submitting!